Civil Engineering CASE STUDIES

Supercharger Electric Charge Points

M&M were responsible for the construction of 24 Tesla Supercharger Points and associated civil works in Applegreen Service Stations at the following locations:

  • Birdhill
  • Castlebellingham North
  • Castlebellingham South

Thanks to these Supercharger Units, Tesla motorists can:

  • Complete a full charge in 30 minutes.
  • Charge Teslas for free at the Supercharger Locations
  • Have access to a large number of Supercharger points across the UK and Ireland.

The works involved:

  • Creating a Construction Drawing Package
  • Minor civil works including :
    • Setting Out
    • Kerbing
    • Reinstatement
    • Landscaping
    • Trench Excavations and Ducting
    • Supercharger foundations.
  • Construction of the Tesla and ESB substations including switchgear fitout.
  • Electrical cabling, earthing and termination works.
  • Erection of the Tesla charge posts.
  • White lining and signage to the new site.
  • DURATION

    5 Months
  • COMPLETION

    December 2017
  • VALUE

    €380,600.00